Update project submittal status to delivered
  • 01 Jun 2021
  • 1 Minute to read
  • Contributors
  • Dark
    Light
  • PDF

Update project submittal status to delivered

  • Dark
    Light
  • PDF

Article Summary

đź’ˇ Please note

Some jurisdictions don't need to complete this step. If your plan review is delivered automatically after you update the plan review status, you can ignore this step! 👍🏻

In the submittal, click Submittal Details, then update the submittal status to Delivered:
Deliver a permit plan review.png

About submittal status

  • If the status is “Awaiting Packaging”, change the status to “Delivered” and Save. You are done.
  • If the status is “In Review” then that means there is at least one Plan Review Discipline still outstanding. So leave the status as "In Review".

Track submittals that need to be delivered

Submittals tab, delivery queue tab.png